A Feasibility Study Report for four-laning of Indapur to Zarap Section has been approved by the Ministry. Feasibility Study Report and Detailed Project Report from Maharashtra/Goa border to Goa/Karnataka border section have been commissioned by Government of Goa.
The estimated cost of projects including pre-construction activities is Rs.4121 crore as per Feasibility Study Report. The type of construction material is proposed as per relevant IRC codes, Ministry's Standard and Specification and site condition. The Panvel to Indapur section is being constructed with flexible pavement.
The Panvel to Indapur Section is under implementation on PPP model by NHAI as executing agency and M/s Supreme Panvel Indapur Tollways Pvt Ltd as Concessionaire. Maharashtra PWD is executing agency for Indapur to Zarap Section. The mode of delivery of projects for Indapur to Zarap Section may be PPP/EPC model based on financial viability of the project.